Buying Abu Dhabi off-plan means buying a home before it is built under Abu Dhabi Law No. 3 of 2015, regulated by ADREC everywhere except Al Reem and Al Maryah islands, which follow ADGM's rules. Before you sign, the developer must give you a regulator-approved disclosure statement; the sale then goes on the Interim Real Estate Register through DARI and TAMM, with a 2% registration fee, and is not binding until it is registered. Every payment goes into the project's escrow account, which the developer cannot draw on before 20% of construction without bank guarantees. Most Abu Dhabi plans leave half the price or more to handover, and launches are concentrated on Al Reem, Yas, Al Raha Beach, Saadiyat and Masdar City.
Key takeaways
- Two rulebooks: most of the emirate follows Law No. 3 of 2015, amended by Law No. 2 of 2025, under ADREC; Al Reem and Al Maryah islands follow ADGM's Off-Plan Development Regulations 2024 and register on ADGM's AccessRP platform.
- A developer needs a written ADREC permit before it advertises an off-plan project, and six conditions, including an escrow account and an approved disclosure statement, before it can sell a single unit.
- The disclosure statement must include the plans, a schedule of finishes, a two-year service fee budget and the estimated delivery date. If it is not given, you can ask to terminate.
- The sale must go on the Interim Real Estate Register. The seller should apply straight after signing; after 21 days you can apply yourself, and late registration carries an AED 10,000 fine on the seller.
- Escrow money can be used only for construction and project finance. Nothing can be drawn before 20% of construction unless the developer posts bank guarantees worth at least 20% of the construction works.
- Across 28 Abu Dhabi projects we track with a published plan, 22 leave 50% or more of the price to handover, so plan how you will fund the final payment before you book.
- At completion the developer must apply to transfer your unit to the Real Estate Register within 21 days of your final payment; if it does not, you or your lender can ask the regulator to do it.
Buying Abu Dhabi off-plan means agreeing to buy a home before it is finished, under rules written specifically for that risk. This guide follows one purchase from launch day to title deed: which rules apply, what the developer must have in place, what you sign, where your money goes, how the plans are shaped and what happens at handover.
If you are new to buying in the emirate, start with buying property in Abu Dhabi as a foreigner, which covers who can own where, every fee and the Golden Visa. This guide goes deeper on the off-plan part. For the regulator itself, see ADREC explained, and for every area and project, our Abu Dhabi page.
01What does off-plan mean under Abu Dhabi law?
An off-plan sale is a contract that gives you property rights over a unit that exists only on the approved plans. Abu Dhabi treats it as its own kind of transaction, with its own register, its own bank account rules and its own handover procedure.
The main law is Law No. 3 of 2015 on the regulation of the real estate sector, amended by Law No. 2 of 2025. Its implementing decisions fill in the detail: Administrative Decision No. 246 of 2015 on the Interim Real Estate Register, and three 2025 decisions on escrow drawdowns, jointly owned property and refunds when a sale is cancelled. ADREC, the Abu Dhabi Real Estate Centre, publishes all of them in its rules and regulations library.
02Which rules apply: ADREC or ADGM?
It depends on the address. Most of the emirate follows ADREC's rules; Al Reem Island and Al Maryah Island are inside Abu Dhabi Global Market (ADGM), which has its own property regulations and register.
Cabinet Resolution No. 41 of 2023 extended ADGM's jurisdiction to Al Reem Island alongside Al Maryah, and Al Reem's register moved to ADGM's Registration Authority on 1 January 2025. ADGM issued its own Off-Plan Development Regulations 2024 covering off-plan sales, project accounts and the registration of developers and projects, with transactions on its AccessRP platform.
That matters because Al Reem is where the largest number of Abu Dhabi off-plan projects we track are being sold. The principles are similar, but the register, the fees and the platform differ. Our guides to living in Al Reem Island and living in Al Maryah Island set out the ADGM process. The rest of this guide describes the ADREC rules that apply everywhere else.
03What must a developer have before selling off-plan?
A permit to advertise, and six conditions before it sells. You can check most of them yourself.
The advertising permit. Under Article 14 of Law No. 3 of 2015, a developer may not advertise an off-plan project in local or foreign media, or show it at an exhibition, without ADREC's written permit. A developer that markets through a broker must register the brokerage contract.
The six conditions. Article 15 says no unit may be sold off-plan until all of these are in place:
| Condition under Article 15 | What you can check |
|---|---|
| Approval of the project by the competent authorities | The project's registration on DARI |
| The development plan, with initial floor and compound plans, deposited with the register | The draft plan in your disclosure statement |
| A property or contractual right over the land that lets the developer build and sell | Ask who owns the land and on what basis |
| Proof that the developer owns the land | Ask for it; a sub-developer also needs the master developer's consent |
| A project escrow account opened | The escrow details on DARI, matched to your contract |
| The regulator's approval of the disclosure statement | A signed statement in your hands before you sign |
If a salesperson asks for money before the project is registered, or wants a payment to an account that is not the project's escrow account, stop. The law makes no exception for an early booking.
04How do Abu Dhabi launches work?
Large Abu Dhabi launches usually run in stages: an expression of interest (EOI), a priority or VIP sale, then the public launch. The EOI is a deposit that holds your place in the queue to choose a unit; it is not yet a purchase.
Modon's Wadeem Gardens on Hudayriyat Island is a typical example: an AED 50,000 EOI from 18 to 28 September 2026, VIP sales on 29 September and the launch on 1 October. Aldar's Sei Saadiyat and Talay both launched in September 2026.
The laws reviewed for this guide do not regulate EOIs as such, so the terms are the developer's. Before you pay one, get in writing:
- Is it refundable, in full, if you do not buy, and how quickly?
- Does it fix anything: a price, a unit, a position in the queue?
- Who holds the money, and is it credited to your booking if you buy?
- When does the sale and purchase agreement follow, and when is the sale registered?
From the reservation onwards the statutory protections apply: the disclosure statement, the register and escrow. See today's releases on new launches.
05What is in the disclosure statement?
It is the developer's signed, regulator-approved description of what you are buying, and you must receive it before you sign. Article 42 of Administrative Decision No. 25 of 2025 lists what it must contain.
- The project. Land uses in the building or community, facilities in the common areas, any special use of your unit such as serviced apartments, and any sustainability features.
- The plans. The compound or sub-development plan, the building or compound management regulation, and a draft floor or compound plan showing your unit's area.
- The finishes. A schedule of materials and finishes for your unit and the common areas.
- The running costs. A budget for the first two financial years after completion, and an estimate of the service fees for your unit in those years.
- The dates. An estimated construction start, if work has not begun, and an estimated delivery date.
- The register. A statement that you must register the purchase on the Interim Real Estate Register, and what happens if you do not.
Why it matters to you. If the developer does not provide the statement, you can ask to terminate the contract. If any of it proves materially inaccurate or incomplete within two years of the unit being transferred to you, the developer is liable for the damage you suffer. Keep it with your contract.
06How does interim registration on DARI work?
Every off-plan sale goes on the Interim Real Estate Register, which ADREC keeps through DARI and TAMM. Under Article 27 of Law No. 3 of 2015, the sale is not binding on you, the developer or anyone else until it is registered.
Who applies, and when. Administrative Decision No. 246 of 2015 puts the duty on the seller, usually the developer, immediately after the contract is signed. If the seller has not registered within 21 days, you can apply yourself and recover the cost from the seller, deducting it from the price if necessary. A seller who registers late can be fined AED 10,000.
What the application contains. The contract date, the parties, the price, the project's name and registration number, the expected completion date and the unit's details, with a signed copy of the contract and the fee receipt.
Your documents. For an individual buyer: a valid passport, and for a UAE resident a residence visa and Emirates ID, or for a non-resident an identification document the regulator accepts, plus an address, phone number and an email the regulator can use for notices. A company buyer adds its licence, constitution, shareholder details and a board resolution naming its signatory.
What you get. Once registered, ADREC notifies both parties of the registration and the registered contract number. Keep that notice with the contract; it is your proof that the sale binds.
The fee. The registration fee is 2% of the price, split equally between buyer and seller unless the contract says otherwise, with a TAMM electronic fee of AED 450. A developer cannot add its own registration fees: Article 16 limits it to an administration fee within the regulator's cap, set at AED 5,000. The worked costs are in buying property in Abu Dhabi as a foreigner.
07What does Law No. 3 of 2015 do with your money?
It ring-fences it in a project escrow account and limits what the developer can spend it on. These are the provisions a buyer relies on.
- One account per project, and per phase. Article 18 requires an escrow account for each project; a project built in stages needs one for each stage. Every payment you make, and every payment your lender makes, goes into it.
- Only for the project. Escrow money may pay only for building the project and its finance. It may not pay for the land or for broker commission.
- Nothing before 20%. The developer cannot draw on the account until at least 20% of construction is complete. Administrative Decision No. 24 of 2025 allows earlier drawdowns only against bank guarantees worth at least 20% of the construction works, backed by an engineering report no more than 30 days old.
- Brokers pay in too. A broker who markets the project must deposit the price into the escrow account and may not take commission out of it first.
- The developer's lender pays in. If the developer borrows against the land to build, the bank must pay the loan into escrow, not to the developer, and your unit is released from that mortgage once you have paid in full.
- Safe from creditors. Escrow funds cannot be seized by the developer's creditors, except in the cases the law lists, such as a cancelled or abandoned project.
- Open to you. Anyone who has paid into the account can see its statements held by the bank and take copies. The bank reports to the regulator every three months.
- A defects reserve. At least 5% of the project's value stays in the account for a year after the completion certificate.
What escrow does not do is guarantee the price, the rent or the handover date. ADREC's powers when a project is late or fails, and its procedure if a buyer stops paying, are set out in ADREC explained.
08How are Abu Dhabi payment plans shaped?
Weighted towards handover. Of the 28 Abu Dhabi projects we track with a published plan, 22 leave half the price or more to pay at handover, and the most common split is 50/50.
What the law says. Article 15 of Law No. 3 of 2015 says the buyer pays according to the actual completion of construction, unless agreed otherwise with the developer. Article 17 lists a developer's refusal to link payments to construction stages as a fundamental breach. Most contracts do agree a schedule, so read whether your instalments fall due on dates or at construction milestones.
Booking amounts are low. Five per cent on booking is the most common first payment in the plans we track, with several at 10%. Remember that the 2% registration fee and any administration fee fall due when the sale is registered, alongside the deposit.
The handover payment is large. On a 50/50 plan, an AED 2 million apartment leaves AED 1 million to pay at handover. The Central Bank caps an off-plan mortgage at 50% of the property's value, and banks set their own terms on top, so check early how much a lender would advance at handover and what you would need in cash.
Extended plans. Some Abu Dhabi plans push most of the price to the end through a mortgage. Wadeem Gardens, for example, takes five instalments of 5% and then 75% in April 2031. That keeps the cash you commit during construction low, but the final payment depends on finance being available when it falls due.
The Golden Visa. For an off-plan home, Abu Dhabi asks for proof that at least AED 2 million has already been paid to the developer, on a property worth at least AED 2 million. On a handover-weighted plan you may qualify only late in the build. See the Golden Visa and UAE property.
Compare structures on our payment plans page and in off-plan payment plans in the UAE, and borrowing in off-plan mortgages in the UAE.
09Where are Abu Dhabi's off-plan launches concentrated?
On the islands and the waterfront. Of the 73 Abu Dhabi projects we tracked on 5 November 2026, about two-thirds were in five areas: Al Reem Island, Yas Island, Al Raha Beach, the Saadiyat Cultural District and Masdar City.
The tables below list every project we track in those five areas, with today's starting price, payment plan and handover date.
Al Reem Island
Abu Dhabi's tower district beside downtown, mostly apartments, and inside ADGM, so sales are registered on AccessRP. See living in Al Reem Island.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Radiant Marina Towers | Radiant Real Estate | Apartment | On request | On request | Dec 2027 | Under construction |
| A1LA Residence | Object 1 | Apartment · Duplex | On request | On request | Q4 2028 | Selling |
| ONE Residence | One Development | Apartment · Duplex | AED 1.49M | 50/50 | 2028 | Selling |
| Radiant Waves Tower | Radiant Real Estate | Apartment · Duplex | On request | On request | Q1 2029 | Selling |
| Rixos Al Reem Residences | East & West Properties | Apartment · Branded residence | On request | On request | On request | Under construction |
| Bab Al Qasr Royal Residence 28 | Burtville Developments | Apartment · Duplex · Branded residence | On request | On request | Q4 2029 | Under construction |
| Flow25 | GAF Property | Apartment · Penthouse · Duplex | On request | 10/40/50 | Apr 2029 | Selling |
| Radiant Bridges Towers | Radiant Real Estate | Apartment · Duplex · Commercial | On request | On request | Q2 2029 | Selling |
| Radiant Terrace | Radiant Real Estate | Apartment · Duplex | On request | On request | Q3 2029 | Selling |
| The Artery Residences | IMKAN Properties | Apartment · Duplex | On request | On request | On request | New launch |
| Bab Al Qasr Beach Resort Residence 77 | Burtville Developments | Apartment · Duplex · Penthouse · Branded residence | On request | On request | Q4 2031 | Selling |
| Riviera Residences Phase 2 | MERED | Apartment · Villa · Duplex · Penthouse | On request | 5/45/50 | On request | New launch |
| Vista 3 by Reportage | Reportage Properties | Apartment · Penthouse | AED 835K | On request | On request | Under construction |
| Marlin Icon | Reportage Properties | Apartment · Duplex · Penthouse | On request | On request | On request | Selling |
| Marlin II by Reportage | Reportage Properties | Apartment | AED 1.6M | On request | On request | Selling |
| The District by Reportage | Reportage Properties | Apartment · Duplex · Penthouse · Townhouse | AED 4.38M | On request | On request | Selling |
Yas Island
The leisure island beside Zayed International Airport, with apartments, townhouses and villas. See living in Yas Island.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Stellar by Elie Saab | Emirates Developments | Branded residence · Apartment · Villa · Penthouse | On request | On request | On request | Selling |
| The Bay Residence 2 | Baraka Real Estate Development | Apartment · Townhouse · Penthouse | On request | On request | On request | Selling |
| The Orchids at Yas Acres | Aldar Properties | Townhouse · Villa | AED 8M | On request | Q1 2031 | Pre-launch |
| Bab Al Qasr Residence 31 | Burtville Developments | Apartment · Duplex · Branded residence | On request | On request | Q1 2029 | Under construction |
| Manchester City Yas Residences by Ohana Phase 2 | Ohana Development | Townhouse · Duplex · Villa · Branded residence | On request | 5/30/65 | 2029 | New launch |
| Perla 2 (Perla Waves) by Reportage | Reportage Properties | Apartment · Duplex | AED 1.9M | On request | On request | Near handover |
| Sama Yas | Aldar Properties | Apartment · Duplex · Penthouse | AED 5.91M | 5/55/40 | Feb 2028 | Selling |
| Aldar Yas Riva Reserve | Aldar Properties | Villa | AED 7.9M | On request | On request | New launch |
| Manchester City Yas Residences by Ohana | Ohana Development | Villa · Townhouse · Apartment · Penthouse · Branded residence | On request | On request | 2029 | Selling |
| The Wadi | Reportage Properties | Apartment | AED 750K | On request | On request | New launch |
| Yas Park Place | Aldar Properties | Apartment · Duplex | On request | On request | Q1 2030 | Selling |
Al Raha Beach
The waterfront district between the city and Yas, mostly apartments and some townhouses. See living in Al Raha Beach.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Bab Al Qasr Canal View Residence 22 | Burtville Developments | Apartment · Duplex · Branded residence | On request | On request | Q2 2029 | Under construction |
| Hilton Residences Abu Dhabi Al Raha | Emirates Developments | Branded residence · Apartment · Townhouse · Penthouse | On request | On request | On request | Selling |
| Brabus Island | Reportage Properties | Apartment · Villa · Townhouse · Penthouse · Branded residence | On request | On request | On request | Selling |
| Bab Al Qasr Sea View Residence 51 | Burtville Developments | Apartment · Duplex · Townhouse · Branded residence | On request | On request | Q4 2029 | Under construction |
| Juman 2 | ICT Real Estate Development | Apartment | AED 3.47M | On request | On request | Selling |
| Luluat Marina at Luluat Al Raha | ICT Real Estate Development | Apartment · Duplex | AED 2.8M | 3/42/55 | On request | Selling |
| Baia by Reportage | Reportage Properties | Townhouse | AED 3.9M | On request | On request | Selling |
Saadiyat Cultural District
The museum district on Saadiyat Island, with prime and branded apartments. See our Saadiyat Island buyer's guide.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Sensi by Reportage | Reportage Properties | Apartment · Townhouse | AED 2.8M | On request | On request | Selling |
| Mamsha Palm | Aldar Properties | Apartment · Duplex | AED 48.32M | 5/25/70 | Q1 2028 | Selling |
| Nobu Residences Abu Dhabi | Aldar Properties | Apartment · Duplex · Penthouse · Branded residence | AED 8.3M | 25/45/30 | Aug 2027 | Selling |
| Mandarin Oriental Residences, Saadiyat Cultural District | Aldar Properties | Apartment · Penthouse · Branded residence | AED 7.29M | 10/55/35 | Q3 2028 | Selling |
| Sei Saadiyat | Aldar Properties | Apartment | AED 2.95M | 5/45/50 | Dec 2030 | New launch |
| The Row Saadiyat | Aldar Properties | Apartment | On request | On request | On request | Selling |
Masdar City
The low-carbon district near the airport, with some of the emirate's lowest entry prices. See living in Masdar City.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Fay Valley | Taraf | Villa · Townhouse | AED 3.14M | 5/35/60 | Q2 2030 | Selling |
| Bab Al Qasr Garden Residence 65 | Burtville Developments | Apartment · Duplex · Penthouse · Branded residence | On request | On request | Q1 2030 | Under construction |
| Royal Park by Reportage | Reportage Properties | Apartment · Penthouse · Townhouse | AED 720K | On request | On request | Under construction |
| Plaza 2 by Reportage | Reportage Properties | Apartment · Townhouse | AED 500K | On request | On request | Under construction |
| Sila by Reportage | Reportage Properties | Apartment · Townhouse | AED 2.8M | On request | On request | Selling |
Outside these five, newer coastal and island destinations are opening up: Hudayriyat Island, Ramhan Island, Fahid Island, and Al Jurf and Ghantoot on the coast towards Dubai. Inland, Zayed City and Al Shamkha offer villa communities. For the official rents in each area, see Abu Dhabi rents by area.
10What happens at handover?
Handover in Abu Dhabi is a sequence: the building is certified, the plans are registered, you pay the balance and your unit moves to the main register with a title deed.
- Completion certificate. The municipality issues a completion certificate once the project is built according to its permits. The developer must tell you the date of the building works' completion and of that certificate, and you can rely on the certificate's date for your legal guarantees.
- Plans registered. Within 60 days of the certificate, the developer must deposit the final floor or compound plans with ADREC, which can extend that by up to 30 days.
- Size check. Your unit's final area is compared with the contracted area. Under 5% difference changes nothing; between 5% and 10% the price moves in proportion; over 10% you can choose to pay or cancel if larger, or take the reduction or cancel if smaller.
- Final payment and inspection. You pay the balance due on handover and inspect the unit. Until it is delivered, the developer bears the unit's running costs, under Article 38 of Administrative Decision No. 25 of 2025, and if it collects service charge money before the completion certificate, it may do so no more than three months before the money is due to be spent.
- Transfer to the Real Estate Register. Within 21 days of your final payment, the developer must apply to transfer the unit into your name. TAMM lists AED 900 plus AED 50 for the transfer.
- If the developer does not transfer. You or your lender can ask the regulator to enforce it. The developer then has 21 days to explain, after which the regulator can transfer the unit itself, with the developer bearing the cost unless agreed otherwise.
After handover. The developer must repair defects under the law's guarantees without charging them to owners or the management company, and the 5% retention stays in escrow for a year. If a delivery slips more than six months beyond the developer's committed schedule, ADREC may impose a delay penalty paid to buyers, unless the delay was beyond the developer's control.
Snag the unit carefully and in writing before you accept the keys; the checklist in our handover process guide works in Abu Dhabi too, though the registers and fees differ.
11Can you sell before completion?
Yes. Units on the Interim Real Estate Register can be sold, mortgaged or otherwise disposed of under Article 29 of Law No. 3 of 2015 and Article 8 of Administrative Decision No. 246 of 2015.
- It is a new registration. A resale is a new disposition and must itself go on the Interim Real Estate Register, with the registration fee, before it binds.
- Pass on the disclosure statement. Before you sign a resale, you must give the new buyer a full copy of your disclosure statement. If you do not, the new buyer can ask to terminate.
- Check the developer's conditions. Developers set their own requirements before they allow a resale, often a minimum share of the price paid and a no-objection letter. Modon, for example, allows resale at Hudayriyat Golf Estates once at least 20% has been paid. Read your contract before you buy if an early exit is part of the plan.
- Settle any mortgage. A lender registered on the unit must consent or be repaid.
12What if you cannot keep paying?
The developer must follow a set procedure before it can cancel your purchase: notice to pay within 60 days, notice to ADREC, and an attempt at an amicable settlement. Only then can your name be removed from the register and the unit resold after 30 days.
What the developer may keep depends on how complete the project is, under Administrative Decision No. 165 of 2025, and the rest is refunded from escrow. The steps and the deduction table are set out in ADREC explained. If you see trouble coming, talk to the developer early; a resale or a revised schedule is usually better than a termination.
13Checklist before you pay
- The address is under ADREC or ADGM, and you know which register your sale goes on.
- The project is registered on DARI, with an escrow account and a completion rate.
- The advert carries a permit, and the person selling holds an ADREC licence.
- Any EOI terms are in writing: refundable, what it fixes, who holds the money.
- You have a signed disclosure statement with the plans, finishes, two-year service fee estimate and delivery date.
- The agreement says who pays the 2% fee, the administration fee and the delay terms.
- Every payment goes to the project's escrow account, never to an individual.
- The sale is on the Interim Real Estate Register, and you have the registration notice.
- You know how you will fund the handover payment, and when you reach any Golden Visa threshold.
- You know the developer's resale conditions if you might sell early.
14Key terms
- ADREC. The Abu Dhabi Real Estate Centre, the emirate's property regulator, within the Department of Municipalities and Transport.
- ADGM. Abu Dhabi Global Market, the financial free zone covering Al Maryah and Al Reem islands, with its own property register.
- DARI. ADREC's platform for projects, escrow details, completion rates and transactions.
- TAMM. The Abu Dhabi government services portal, through which registrations are filed and fees paid.
- Interim Real Estate Register. The register of off-plan sales, resales and mortgages before completion.
- Disclosure statement. The developer's signed, regulator-approved description of the unit and project, given before you sign.
- Escrow account. The project's bank account, managed by an approved bank, into which all buyers' payments go.
- Completion certificate. The municipality's certificate that the project is built according to its permits.
- EOI. An expression of interest: a deposit to join the queue at a launch, on the developer's terms.
15Where to go next
- Buying property in Abu Dhabi as a foreigner: zones, every fee and the Golden Visa
- ADREC explained: the regulator, defaults, delays and penalties
- Abu Dhabi rents by area: official rents from registered leases
- Off-plan payment plans in the UAE
- All Abu Dhabi areas and projects
Tell us your budget and what you want the home for, and we will send the Abu Dhabi off-plan projects that fit, with today's availability checked.
On live projectsSee these plans on live projects.
100 / 0Wadeem GardensModon Properties · from AED 8,700,000
5 / 45 / 50Sei SaadiyatAldar Properties · from AED 2,950,000
50 / 50TalayAldar Properties · from AED 13,500,000Compare payment plans side by side for projects with a verified schedule.
FAQQuestions buyers ask.
Can foreigners buy off-plan property in Abu Dhabi?
Yes, inside Abu Dhabi's investment zones, which include Yas, Saadiyat, Al Raha Beach, Masdar City, Hudayriyat and the ADGM islands of Al Reem and Al Maryah. Any nationality can buy, and you do not need to live in the UAE. The off-plan sale is registered with ADREC, or with ADGM on Al Reem and Al Maryah.
Is buying off-plan in Abu Dhabi safe?
The law protects your money and your contract. Each project must have an escrow account, the developer cannot draw on it before 20% of construction unless it posts guarantees, 5% of the project value is held back for a year after completion, and a sale is not binding until it is on the Interim Real Estate Register. The law does not protect the resale price or rent.
What is the Interim Real Estate Register?
The register ADREC keeps for every sale, resale and mortgage of a unit sold off-plan. Under Article 27 of Law No. 3 of 2015, an off-plan sale is not binding on the parties or anyone else until it is registered there. At completion the unit moves to the main Real Estate Register and you receive a title deed.
How do I register an off-plan purchase on DARI?
The seller, usually the developer, applies through DARI and TAMM straight after the contract is signed, with the signed contract, proof that the fee is paid and the buyer's details. A non-resident buyer gives a passport copy and an accepted identification document. If the seller has not registered within 21 days, the buyer can apply and recover the cost.
What fees do I pay when buying off-plan in Abu Dhabi?
A 2% registration fee, split between buyer and seller unless the contract says otherwise, a TAMM electronic fee of AED 450, a developer administration fee capped at AED 5,000, and AED 900 plus AED 50 to transfer to the main register at handover. Confirm the current amounts on TAMM before you pay.
Can a developer use my payments before the building is started?
Not for anything other than the project. Escrow money can pay only for construction and project finance, never for the land or broker commission, and nothing can be drawn before 20% of construction unless the developer gives ADREC bank guarantees worth at least 20% of the construction works.
Can I sell an Abu Dhabi off-plan property before handover?
Yes. Units on the Interim Real Estate Register can be resold or mortgaged. The resale is registered as a new transaction, and you must hand the new buyer a full copy of your disclosure statement. Developers set their own conditions, such as a minimum share of the price paid, so check your contract.
What happens if an Abu Dhabi off-plan project is delayed?
If delivery is more than six months later than the schedule the developer committed to, ADREC may impose a delay penalty paid to buyers, unless the delay was beyond the developer's control. If a project does not start and buyers of at least 5% of sold units complain, the regulator can investigate and cancel it, returning escrow money.
Where are most off-plan projects in Abu Dhabi?
On the islands and the waterfront. Of the 73 Abu Dhabi projects we tracked on 5 November 2026, Al Reem Island had 17, Yas Island 12, Al Raha Beach 8, and the Saadiyat Cultural District and Masdar City 6 each.
Sources & methodWhere these figures come from.
Sources
- adrec.gov.ae: Regulations
- adrec.gov.ae: Property ownership
- adrec.gov.ae: Faqs
- adrec.gov.ae: Developer journey
- adrec.gov.ae: Press 27 adrec H1 2026 transaction report
- dari.ae
- tamm.abudhabi: RegistertheSaleofanOffPlanPlotorUnit
- tamm.abudhabi: TransferUnitfromInitialReregistertoRealEstateReregister
- tamm.abudhabi: RequesttoRegisteraUnitforFirstSale
- dmt.gov.ae: DMT Issues Regulatory Decisions to Enhance Transparency and Governance in Real Estate Sector
- adgm.com
- added.gov.ae: Visa for real estate investors
- Central Bank of the UAE Rulebook: Regulations regarding mortgage loans
- modon.com: Wadeem gardens
- modon.com: Hudayriyat golf estates
What we could not verify
- ADGM's registration fees and project account rules for off-plan sales on Al Reem and Al Maryah are not given, because ADGM's regulation text could not be opened; ask the developer and ADGM's Registration Authority what applies before you pay.
- Expressions of interest are not regulated as such in the laws reviewed; whether an EOI is refundable, and whether it fixes a price, depends on the developer's own terms, so get them in writing.
- TAMM fee figures (the 2% fee, the AED 450 electronic fee and AED 900 plus AED 50 for the transfer) are restated from TAMM service pages as indexed and our earlier guide; confirm the current amounts on TAMM before paying.
5 Nov 2026 · Reviewed by OffPlan Insider Research. First published 5 Nov 2026, updated 9 Nov 2026. Data: laws and decisions as published in ADREC's rules and regulations library; payment-plan and project counts from OffPlan Insider project data on 5 November 2026.