RAK Properties aims for more than 1,400 homes ready by year-end, with Cape Hayat over 98% built

RAK Properties made AED 809.72 million of revenue in the first nine months of 2026 and lifted its sales backlog to AED 3.18 billion. Its update also gives build progress on each Mina Al Arab project.

Published 3 min read
Render of the four Quattro Del Mar towers on Hayat Island at sunset, joined by sky bridges
Quattro Del Mar on Hayat Island, Mina Al Arab, which was 64.1% complete at the end of September. Render: RAK Properties.

RAK Properties expects more than 1,400 homes to be ready for handover by the end of 2026, which it says will be a record year for deliveries. The Ras Al Khaimah developer set out the target in its nine-month update on 6 November.

Revenue for the nine months to 30 September was AED 809.72 million. The sales backlog, the value of homes sold but not yet delivered, rose to AED 3.18 billion from AED 2.88 billion a year earlier.

01The nine months in figures

Measure Nine months to 30 September 2026
Revenue AED 809.72 million
Gross profit AED 312.59 million
EBITDA AED 202.71 million
Net profit after tax AED 111.37 million
Homes sold 260, worth AED 476 million
Average price per home AED 1.83 million (AED 1.65 million a year earlier)
Average selling rate AED 1,916 per sq ft
Sales backlog AED 3.18 billion (AED 2.88 billion a year earlier)
Total assets AED 8.9 billion

RAK Properties, 6 November 2026.

The developer said it is not using blanket discounts. It has been meeting international buyers through its broker network after roadshows in Europe.

02Handovers so far

In the nine months, 748 homes became available for handover at Bay Residences 2, Granada Extension and Bay Views. RAK Properties handed over 356 homes to their owners across its completed projects, including Bay Residences, Granada, Marbella, Malibu, Flamingo and Bay Views.

The next deliveries are at Beach Houses and Cape Hayat, both in Mina Al Arab. They are due in the last quarter of the year.

03Construction progress on each project

Project Progress at 30 September 2026
Bay Views Complete; handovers under way
Beach Houses, phases 1 and 2 Substantially complete; utility connections and readiness checks to follow
Cape Hayat Over 98% complete; home previews under way in Towers 1 and 2
Quattro Del Mar 64.1% complete
Edge 34% complete
Skai 14.9% complete
Mirasol I 6.5% complete; main contractor on site
Mirasol II Main contractor to be appointed this quarter
Solera Enabling works complete; main contract to follow
Enta Mina 7% complete overall
Anantara Residences Mina Villa main contract awarded; apartment piling and enabling works 84% complete

RAK Properties, 6 November 2026.

At Cape Hayat, Civil Defence approvals are in place for Towers 3 and 4. The landscaping, pool and shared amenities are ready, the developer said.

04What comes next

RAK Properties plans to bring The Strand and its first community, Lunara on The Strand, back to market in early 2027. The Strand is on the mainland at Al Marjan Beach.

The Four Seasons Resort and Residences Ras Al Khaimah at Mina is due to go on sale in the first half of 2027. The developer has launched projects worth AED 5.4 billion since 2025, with more than 5,000 homes in planning, design, construction or delivery.

It holds about 924,862 sq m of undeveloped land across Mina and The Strand. That could support about 1.44 million sq m of floor space.

05What it means if you are buying

If you own a home at Cape Hayat or Beach Houses, handover is the next step. Our handover guide and snagging guide cover what to check before you take the keys.

If you are buying at an earlier stage, use the progress figures. They show how far each building has come and how much of the build is still to go before your final payments fall due.

For background on the emirate, see our guides to buying property in Ras Al Khaimah and living in Mina Al Arab. You can browse all current launches on our RAK Properties developer page.

ProjectsProjects in this story.

SourcesWhere this story comes from.

Sources

  1. RAK Properties PJSC: RAK Properties on track for record home deliveries by end of year as developer meets period of change and challenge with sustained performance and results, 6 November 2026
  2. Khaleej Times: RAK Properties targets record home handovers by year-end despite sales slowdown, 6 November 2026

Corrections

  • No corrections to this story. If something has changed or is wrong, tell us and we will correct it and log the change here.

7 Nov 2026, 21:23 GST · Reported by OffPlan Insider Newsdesk, checked against the developer's own material before publication.

Want the details on Cape Hayat?

We confirm current prices, plans and availability directly with the developer, then send you what fits.

  1. We check with the developerToday’s units, prices and plan
  2. You get the detailsBy phone or email, your choice
  3. You reserve directBooking is with the developer

No consultation fee · You book directly with the developer