The Dubai Loop is an underground passenger tunnel network that Dubai's Roads and Transport Authority (RTA) is building with the US firm The Boring Company, using electric vehicles in 3.6 m tunnels. Under the agreement signed on 3 February 2026, the first phase is a 6.4 km pilot with four stations linking the Dubai International Financial Centre (DIFC) and Dubai Mall, costing about AED 565 million. The full route runs up to 22.2 km with 19 stations, connecting Dubai World Trade Centre and the financial district with Business Bay, for about AED 2 billion. The RTA gives durations rather than dates: about one year for the pilot once design and preparations are complete, and about three years for the full route.
Key takeaways
- The Dubai Loop is an RTA project with The Boring Company: tunnels of 3.6 m diameter carrying passengers in vehicles, designed for first- and last-mile trips and links between key destinations.
- The pilot is 6.4 km with four stations between DIFC and Dubai Mall, at about AED 565 million, and is expected to carry about 13,000 passengers a day.
- The full route is up to 22.2 km with 19 stations, linking Dubai World Trade Centre and the financial district with Business Bay, at about AED 2 billion and about 30,000 passengers a day.
- The plan changed between 2025 and 2026. The February 2025 memorandum studied a 17 km tunnel with 11 stations; the February 2026 agreement replaced those figures.
- The RTA gives durations, not opening dates: about one year for the pilot after design and preparations, about three years for the full route. In September 2026 boring machine assembly and segment casting were under way.
- The districts on the route, DIFC, Downtown Dubai, Business Bay and Trade Centre, are already served by the Metro Red Line. The Loop adds short links between them; it does not replace the metro.
- Buy for the building, the price and the existing transport. Exact sites for most Loop stations are still to be confirmed, so do not pay extra for a promised station next door.
01What is the Dubai Loop?
The Dubai Loop is an underground passenger transport network that Dubai's Roads and Transport Authority (RTA) is building with The Boring Company, a US tunnelling firm. Passengers travel in electric vehicles through tunnels 3.6 m in diameter.
The RTA describes it as designed for flexible urban mobility: first- and last-mile trips and quick connections between key destinations. It is meant to sit alongside the Dubai Metro, not to replace it.
The RTA and The Boring Company signed an agreement to begin implementation on 3 February 2026, at the World Governments Summit. A year earlier, on 13 February 2025, they had signed a memorandum to study the idea.
This guide sets out the official route, numbers and timeline, and what the Loop does and does not change if you are buying a home in the districts it serves.
02What is the Dubai Loop route?
The pilot links DIFC and Dubai Mall over 6.4 km with four stations. The full route runs up to 22.2 km with 19 stations, connecting Dubai World Trade Centre and the financial district with Business Bay.
| Pilot (phase one) | Full route | |
|---|---|---|
| Length | 6.4 km | Up to 22.2 km |
| Stations | 4 | 19 |
| Districts | DIFC and Dubai Mall | Dubai World Trade Centre and the financial district to Business Bay |
| Approximate cost | AED 565 million | AED 2 billion |
| Expected passengers | About 13,000 a day | About 30,000 a day |
| Time to deliver | About one year after design works and preparations | About three years |
The tunnels. The RTA gives a diameter of 3.6 m, dedicated to vehicles. That is far narrower than a metro tunnel, which is why the system carries passengers in cars rather than trains.
Station sites. The official announcements name the districts the route connects rather than a full list of station sites. Before you rely on a station being close to a particular building, ask the RTA or check its published route plans.
03How has the Dubai Loop plan changed since 2025?
It has become shorter at first and longer overall. The 2025 memorandum studied a 17 km tunnel with 11 stations; the 2026 agreement starts with a 6.4 km pilot and plans a full route of up to 22.2 km with 19 stations.
February 2025: the study. The memorandum signed at the World Governments Summit 2025 was an agreement to study the project. The Dubai Media Office described a 17 km tunnel with 11 stations and a capacity of more than 20,000 passengers an hour, as part of a long-term plan for an underground network across the city. The RTA supplied geotechnical, utility, structural, environmental and transport-standards data for the study.
February 2026: the agreement to build. The agreement signed a year later set the pilot and full-route figures in the table above, with costs and delivery periods. The next day, the Dubai Media Office reported a review of the Dubai Loop and the Glydways autonomous transit project.
If you read older articles quoting 17 km and 11 stations, they describe the study, not the plan now being built.
04When will the Dubai Loop open?
There is no official calendar date. The RTA says the pilot will be delivered about one year after design works and preparations are complete, and the full route in about three years.
On 29 September 2026 the Dubai Media Office reported a progress review with The Boring Company. Preliminary works were continuing in parallel workstreams, the tunnel boring machine was being assembled and concrete tunnel-lining segments were being cast.
What that means in practice. Boring machine assembly and segment casting come before tunnelling. The pilot clock of about one year runs from the end of design and preparation, so a firm opening date is on request from the RTA.
05What is confirmed, and what is still to be decided?
The route's districts, length, station count, costs, expected passengers and delivery periods are confirmed in the February 2026 agreement. Station addresses, fares, vehicles and a calendar opening date are on request from the RTA.
| Question | Confirmed by the RTA | Still to be confirmed |
|---|---|---|
| Route | Pilot between DIFC and Dubai Mall; full route from Trade Centre and the financial district to Business Bay | The exact alignment street by street |
| Stations | 4 on the pilot, 19 on the full route | Names and sites of individual stations |
| Length | 6.4 km pilot; up to 22.2 km full route | Final length once the full alignment is fixed |
| Cost | About AED 565 million pilot; about AED 2 billion full route | None for buyers; fares are separate |
| Passengers | About 13,000 a day pilot; about 30,000 a day full route | Journey times between stations |
| Timing | About one year for the pilot after design and preparations; about three years for the full route | A calendar opening date |
| Vehicles | Electric vehicles in 3.6 m tunnels | Vehicle type, number and speed |
| Fares | None stated | Fares and how they link with Nol cards |
The column on the right is where marketing claims tend to appear. If an advert gives a station name next to a building, a journey time or an opening year, ask for the RTA document it comes from.
06How many passengers will the Dubai Loop carry?
The RTA expects the pilot to carry about 13,000 passengers a day and the full route about 30,000 a day.
For scale, the Dubai Media Office said in May 2026 that the metro and tram network carried about 295 million trips in 2025, an average of about one million a day. The Loop is a short-trip link in the city centre, not a mass-transit line on that scale.
07Which communities will the Dubai Loop serve?
The route serves Dubai's central business and residential districts along Sheikh Zayed Road: DIFC, Downtown Dubai around Dubai Mall, Business Bay and the Trade Centre area. Each is already on the Metro Red Line.
| District | On the Loop | Existing Metro Red Line station | Our area page |
|---|---|---|---|
| DIFC | Pilot, and full route | Financial Centre | DIFC |
| Downtown Dubai (Dubai Mall) | Pilot, and full route | Burj Khalifa/Dubai Mall | Downtown Dubai |
| Business Bay | Full route | Business Bay | Business Bay |
| Dubai World Trade Centre | Full route | World Trade Centre | Zabeel, next door |
DIFC
DIFC, the Dubai International Financial Centre, is the financial district on Sheikh Zayed Road between Trade Centre, Zabeel and Downtown Dubai. It mixes offices with homes, galleries and restaurants, and is one end of the Loop's pilot route. Our DIFC area page covers the district in full.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Akala Residences | Arada | Apartment · Penthouse · Branded residence | AED 3.79M | 10/50/40 | Q4 2029 | Selling |
| Four Seasons Private Residences Dubai at DIFC | H&H | Branded residence · Apartment · Penthouse | On request | On request | 2029 | Under construction |
Downtown Dubai
Downtown Dubai is Emaar's district around the Burj Khalifa and Dubai Mall, and the other end of the pilot route. It is served today by Burj Khalifa/Dubai Mall station on the Red Line. See our Downtown Dubai area page for every project and price.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| DWTN Residences | Deyaar | Apartment · Duplex · Penthouse | On request | On request | On request | Selling |
| Binghatti Skyblade | Binghatti Developers | Apartment | AED 1.76M | 20/50/30 | Q4 2027 | Selling |
| Fairmont Residences Solara Tower | SOL Properties | Apartment · Penthouse · Branded residence | On request | 20/40/40 | Q3 2027 | Under construction |
| Inaura Downtown | Arada | Apartment · Duplex · Penthouse · Branded residence | AED 3.59M | 10/40/50 | On request | Selling |
| Mercedes-Benz Places | Binghatti | Binghatti Developers | Apartment · Penthouse · Branded residence | AED 11.5M | 20/50/30 | Dec 2026 | Near handover |
| Rove Home Downtown Dubai | IRTH Group | Apartment · Branded residence | On request | On request | 2026 | Near handover |
| Sofitel Residences Dubai City View | CITYVIEW Developments | Branded residence · Apartment · Duplex · Penthouse | AED 2.61M | 20/30/50 | Q4 2029 | Selling |
| Trump International Hotel & Tower Dubai | DarGlobal | Apartment · Penthouse · Branded residence | On request | On request | Dec 2031 | Selling |
Business Bay
Business Bay is the mixed-use district beside Downtown Dubai along the Dubai Water Canal, and the southern end of the Loop's full route. It is also on the planned Gold Line: in April 2026 the Dubai Media Office announced a 42 km, 18-station underground line from Al Ghubaiba to Jumeirah Golf Estates, with an interchange to the Red Line at Business Bay, due to open on 9 September 2032. See our Business Bay area page.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Bayz 101 by Danube | Danube Properties | Apartment | AED 1.32M | On request | Jun 2029 | Selling |
| Bayz 102 by Danube | Danube Properties | Apartment · Penthouse | AED 2.59M | On request | Dec 2029 | Selling |
| One River Point | Ellington Properties | Apartment · Duplex · Penthouse | On request | On request | On request | Under construction |
| Burj Binghatti Jacob & Co Residences | Binghatti Developers | Apartment · Penthouse · Branded residence | AED 8.4M | 20/50/30 | Jun 2027 | Selling |
| Bugatti Residences by Binghatti | Binghatti Developers | Apartment · Penthouse · Branded residence | AED 19.4M | 20/50/30 | Aug 2027 | Selling |
| Binghatti Skyhall | Binghatti Developers | Apartment | AED 1.3M | 20/50/30 | On request | Near handover |
| Binghatti Aquarise | Binghatti Developers | Apartment | AED 2M | 20/50/30 | Q1 2027 | Selling |
| Binghatti Skyrise | Binghatti Developers | Apartment | AED 2.54M | 20/50/30 | Q4 2026 | Near handover |
| VELA, Dorchester Collection, Dubai | OMNIYAT | Apartment · Duplex · Penthouse · Branded residence | On request | On request | Q4 2027 | Selling |
| Chic Tower by DAMAC | DAMAC Properties | Apartment · Branded residence | AED 4.71M | On request | Q2 2027 | Selling |
| Safa Two de GRISOGONO | DAMAC Properties | Apartment · Penthouse · Branded residence | AED 3.26M | On request | Q2 2027 | Selling |
| Al Habtoor Tower | Al Habtoor Group | Apartment | On request | 10/15/35/40 | 2026 | Selling |
| Tiger Sky Tower | Tiger Properties | Apartment · Penthouse | AED 2.5M | On request | On request | Selling |
| Altitude de GRISOGONO by DAMAC | DAMAC Properties | Apartment · Branded residence | AED 2.75M | On request | Q1 2028 | Selling |
| Avarra by Palace | Emaar Properties | Apartment · Penthouse · Branded residence | AED 2.71M | 10/80/10 | Jun 2031 | Selling |
| Canal Crown by DAMAC | DAMAC Properties | Apartment · Branded residence | AED 3.5M | 60/40 | Q4 2027 | Selling |
| Canal Heights de GRISOGONO by DAMAC | DAMAC Properties | Apartment · Branded residence | AED 12.46M | On request | Q2 2027 | Selling |
| Couture by Cavalli | DAMAC Properties | Apartment · Penthouse · Branded residence | AED 21.9M | 60/40 | Q4 2028 | Selling |
| DG1 by DarGlobal | DarGlobal | Apartment | On request | On request | Dec 2027 | Selling |
| Rove Home Marasi Drive | IRTH Group | Apartment · Branded residence | On request | On request | 2027 | Selling |
Trade Centre and Zabeel
The full route's northern end is Dubai World Trade Centre, the convention and exhibition district. Zabeel, the district next to it between DIFC and Zabeel Park, is where Emaar is building Address Residences Zabeel. See our Zabeel area page.
| Project | Developer | Homes | From | Payment plan | Handover | Status |
|---|---|---|---|---|---|---|
| Address Residences Zabeel | Emaar Properties | Apartment · Penthouse · Branded residence | AED 2.96M | On request | On request | Selling |
For the whole city, see all off-plan projects or the latest launches.
08How does the Dubai Loop fit with the Dubai Metro?
It adds short links between places the metro already reaches. The Red Line runs along Sheikh Zayed Road through the same districts; the Loop is designed for first- and last-mile trips and connections between destinations.
Three rail projects shape transport in and near these districts over the next few years.
| Project | What it is | Status and date |
|---|---|---|
| Dubai Loop | Underground vehicle tunnels, 6.4 km pilot and up to 22.2 km full route | Implementation agreement February 2026; about one year for the pilot after design and preparation |
| Metro Blue Line | 30 km, 14 stations in eastern Dubai, joining the Green and Red Lines | Under construction; opening 9 September 2029 |
| Metro Gold Line | 42 km, 18 stations, fully underground, Al Ghubaiba to Jumeirah Golf Estates via Business Bay | Approved April 2026; opening 9 September 2032 |
Our Dubai Metro Blue Line guide covers the eastern line in detail.
09What does the Dubai Loop mean if I am buying a home?
Treat it as a possible convenience, not a reason to buy or a reason to pay more. Base your decision on the building, the price, the developer and the transport that exists today.
The districts are already connected. DIFC, Downtown Dubai, Business Bay and Trade Centre have Red Line stations now. A Loop station would shorten some trips within the centre, but the area's connectivity does not depend on it.
Station sites are not fixed in public. Beyond the pilot's two ends, the official releases give districts rather than addresses. Do not accept "a Loop station at the door" without seeing the RTA's plan.
Timing is open. The RTA gives durations, not dates. If transport timing matters to you, compare your building's completion date with the RTA's stated periods and plan on the existing metro.
Construction nearby. Tunnelling and station works can mean road diversions for a period. Ask the developer or the RTA what works are planned near the building you are considering.
10Checklist: judging a property advert that mentions the Dubai Loop
- Ask for the source. Any station site, opening date or journey time should come from the RTA or the Dubai Media Office.
- Check the figures are current. Adverts quoting 17 km and 11 stations are using the 2025 study figures.
- Measure to the existing metro. Note the walking distance to the nearest Red Line station today.
- Read your completion date. Your sale and purchase agreement sets your handover date; transport projects do not change it.
- Verify the project. Check the project and its escrow account on the Dubai Land Department register before paying. Our guide on how to check an off-plan project and developer shows how.
- Price on comparables. Compare price per square foot with similar homes nearby using Dubai Land Department registered sales, not with a future transport link.
- Budget the full cost. Fees, the handover payment and service charges are in our guide to the true cost of buying off-plan.
11Which district suits which buyer?
The four districts on the route are close together but different in character. The Loop does not change that; it shortens some trips between them.
| District | Character | Typical off-plan homes | Worth knowing |
|---|---|---|---|
| DIFC | Financial district with its own common-law courts, galleries and restaurants | A small number of high-end apartments and branded residences | Few launches; most homes are resale |
| Downtown Dubai | Emaar's district around the Burj Khalifa, Dubai Mall and Dubai Opera | Apartments, many in branded and hotel-serviced towers | Pilot station area; busy with visitors |
| Business Bay | Mixed-use towers on the Dubai Water Canal, next to Downtown | The widest choice, from studios to branded penthouses | Also on the planned Gold Line |
| Trade Centre and Zabeel | Convention district beside Zabeel Park | A few large branded schemes | Northern end of the full route |
If you are comparing apartments across these districts, our apartments page and branded residences page list current projects across Dubai.
12How do I follow the Dubai Loop's progress?
Use the RTA's news pages and the Dubai Media Office, which publish the government's announcements on the project. Dated, official statements are the ones to rely on.
For a home you have bought or are about to buy, follow the building rather than the transport. The Dubai Land Department's Project Status service in the Dubai REST app shows a registered project's certified completion percentage.
13Key terms
| Term | What it means here |
|---|---|
| Loop | A tunnel network carrying passengers in road vehicles rather than trains |
| Pilot route | The first, 6.4 km phase between DIFC and Dubai Mall |
| Full alignment | The complete planned route, up to 22.2 km with 19 stations |
| First and last mile | The short trip between a home or office and a main transport line |
| Tunnel boring machine | The machine that excavates the tunnel and places the lining as it advances |
| Lining segments | Precast concrete pieces that form the tunnel wall |
| Memorandum of understanding | An agreement to study or co-operate, which comes before a contract to build |
14Where to go next
If you are choosing between central districts, start with the DIFC, Downtown Dubai and Business Bay area pages, and our overview of Dubai's areas and districts. For the buying steps from reservation to keys, read our guide to buying off-plan property in Dubai.
ProjectsProjects mentioned in this guide.
FAQQuestions buyers ask.
What is the Dubai Loop?
The Dubai Loop is an underground passenger transport system that the RTA is building with The Boring Company. Passengers travel in electric vehicles through tunnels 3.6 m in diameter. The first phase is a 6.4 km pilot with four stations between DIFC and Dubai Mall; the full route is planned at up to 22.2 km with 19 stations.
Where will the Dubai Loop stations be?
The four pilot stations lie on the route between DIFC and Dubai Mall. The full route's 19 stations will connect Dubai World Trade Centre and the financial district with Business Bay. The RTA's announcements give the districts rather than a full list of station sites, so check with the RTA before relying on a station's exact position.
When will the Dubai Loop open?
The RTA gives durations rather than calendar dates. The pilot is due about one year after design works and preparations are complete, and the full route is expected to take about three years to implement. In September 2026 the Dubai Media Office said boring machine assembly and the casting of tunnel-lining segments were under way.
How much does the Dubai Loop cost to build?
The RTA puts the 6.4 km pilot at about AED 565 million and the full route of up to 22.2 km at about AED 2 billion. These are construction costs announced with the February 2026 agreement. Passenger fares are on request from the RTA.
Is the Dubai Loop the same as the Dubai Metro?
No. The Dubai Metro is a rail network of large trains on fixed lines. The Dubai Loop uses smaller electric vehicles in narrow tunnels for shorter trips within the city centre. The districts on the Loop's route are already served by Red Line stations, and the Loop is described as adding first- and last-mile links.
Who is building the Dubai Loop?
The Roads and Transport Authority (RTA) is delivering it with The Boring Company of the United States. The two signed a memorandum to study the project at the World Governments Summit on 13 February 2025, and an agreement to begin implementation at the same summit on 3 February 2026.
Is Downtown Dubai freehold?
Yes. Downtown Dubai, Business Bay and DIFC are areas where foreign buyers can own property outright, and off-plan purchases there are registered with the Dubai Land Department. Check that a project and its escrow account appear on the department's register before you pay.
Is the Dubai Loop the 93 km cycling 'Loop'?
No. The name has also been used for a separate concept for a covered walking and cycling route across Dubai. This guide covers the RTA's underground passenger tunnel with The Boring Company, which is the project with a signed implementation agreement.
Sources & methodWhere these figures come from.
Sources
- mediaoffice.ae: Rta signs agreement with the boring company to commence implementation of dubai loop
- rta.ae: Signing agreemennt with boring company to commence implementation of dubai loop
- mediaoffice.ae: Mohammed bin rashid reviews the dubai loop and glideways projects
- mediaoffice.ae: Hamdan bin mohammed meets the boring company delegation
- mediaoffice.ae: Hamdan bin mohammed attends mou signing between rta and the boring company for the dubai loop
- rta.ae: Hamdan bin mohammed attends mou signing between rta and the boring company for the dubai loop
- rta.ae: Al_Masar_201_Eng.pdf
- mediaoffice.ae: Mohammed bin rashid approves dubai metro gold line
- rta.ae: About metro
- Dubai Legislation Portal: Law No. (7) of 2006
- Dubai Legislation Portal: Law No. (8) of 2007
What we could not verify
- The names and exact sites of the four pilot stations are not given in the RTA and Dubai Media Office releases we opened; press reports name them, but they are not used in the text.
- No calendar opening date for the pilot or the full route appears in an official statement; the RTA gives durations of about one year after design and preparations for the pilot and about three years for the full route.
- Fares, vehicle numbers, vehicle type and operating speed were not stated in the official releases and are not given.
4 Nov 2026 · Reviewed by OffPlan Insider Research. First published 4 Nov 2026.