Skip to content
OffPlan Insider
Guide · Buying processReviewed 4 Nov 2026

Dubai Creek Tower: the official timeline and what it means for Creek Harbour buyers (2026)

Dubai Creek Tower from Emaar's own statements: the design, the foundations built so far, the dated milestones, the metro station beside it, and how to buy a home in Dubai Creek Harbour on facts rather than on the skyline.

OffPlan Insider ResearchWritten and reviewed by the research desk
Published 4 Nov 202611 min read13 sources cited
The short answer

Dubai Creek Tower is the landmark tower Emaar plans at the heart of Dubai Creek Harbour, its 6 sq km community on Dubai Creek beside the Ras Al Khor Wildlife Sanctuary. It was designed by Santiago Calatrava Valls, work began in October 2016, and Emaar reported the pile foundations complete in March 2017 and the pile cap finished in 2018. For the tower's current construction stage, final height or completion date, ask Emaar: none of these is part of the sale contract for a home in Creek Harbour. Buy for the building, the community and the transport that is already dated, such as the Blue Line metro station planned to open on 9 September 2029.

Key takeaways

  1. Dubai Creek Tower is Emaar's planned centrepiece for Dubai Creek Harbour, designed by Santiago Calatrava Valls. Emaar described a slender stem anchored by cables, an oval top, observation decks called the Pinnacle Room and the VIP Observation Garden Decks, and a boutique hotel.
  2. The dated milestones are Emaar's: design unveiled in April 2016, wind tunnel tests in July 2016, groundbreaking in October 2016, pile foundations complete in March 2017 and the pile cap complete in 2018.
  3. The foundations, in Emaar's figures: more than 145 barrette piles 72 m deep, one tested to 36,000 tonnes, under a pile cap about 20 m thick holding 50,000 cubic metres of concrete.
  4. For the tower's current stage, final height and completion date, ask Emaar. None of them appears in the sale and purchase agreement for a Creek Harbour apartment.
  5. Each residential building in Creek Harbour has its own registration with the Dubai Land Department, its own escrow account and its own completion date. The tower's progress does not move your handover.
  6. What is dated is the metro. The RTA's Blue Line stops at Emaar Properties Station in Dubai Creek Harbour, planned to open on 9 September 2029, about 20 minutes from Dubai International Airport.
  7. Emaar puts Dubai Creek Harbour at 7.4 million sqm of residential space and 500,000 sqm of parks and open space, about 10 minutes by car from the airport.

01What is Dubai Creek Tower?

Dubai Creek Tower is the landmark tower Emaar plans at the centre of Dubai Creek Harbour, its waterfront community on Dubai Creek. Emaar unveiled the design in April 2016 as the centrepiece of the community.

The architect is Santiago Calatrava Valls, chosen through an international design competition. Emaar described a design inspired by the lily and evoking a minaret: an elongated oval "bud" on a slender stem, anchored to the ground by cables.

At the top, Emaar's design release described the Pinnacle Room, with fully glazed rotating balconies that extend outside the tower's skin, and the VIP Observation Garden Decks below it, with 360-degree views. The same release mentioned a boutique hotel within the tower.

This guide sets out what is officially on record about the tower, and how to use that when you buy a home in Dubai Creek Harbour. For the full list of projects, prices and payment plans in the community, see our Dubai Creek Harbour area page.

02Where is Dubai Creek Tower?

The tower stands in Dubai Creek Harbour, a 6 sq km community on the bank of Dubai Creek. The community borders the Ras Al Khor Wildlife Sanctuary, a protected wetland known for its flamingos.

Emaar describes Dubai Creek Harbour as twice the size of Downtown Dubai and puts it about 10 minutes by car from Dubai International Airport. Emaar's community pages give about 10 to 15 minutes to Downtown Dubai and the Burj Khalifa, about 5 minutes to the Ras Al Khor sanctuary and about 25 minutes to Dubai Marina. Times vary with traffic.

Emaar develops Dubai Creek Harbour in a joint venture with Dubai Holding, as its 2017 foundation release states.

Schematic, not to scale, of where Dubai Creek Harbour sits on Dubai Creek. Dubai Creek Harbour, 6 sq km, by Emaar, is at the centre, with Emaar's drive-time estimates to Dubai International Airport about 10 minutes, Downtown Dubai about 10 to 15 minutes, Dubai Marina about 25 minutes and the Ras Al Khor Sanctuary about 5 minutes, which borders the community. Emaar Properties Station on the Blue Line is marked, 74 m tall, with service planned from 9 September 2029. Three figures below: 7.4 million sqm of residential space and 500,000 sqm of parks and open space, both Emaar's community figures, and about 40,000 residents served by the station, from the Dubai Media Office in May 2026.
Dubai Creek Harbour's position, with Emaar's drive-time estimates and the RTA's metro station. Schematic, not to scale.

03What has been built so far?

The construction milestones on record are the tower's foundations: the pile foundations, completed in March 2017, and the pile cap above them, completed in 2018. For the current stage of works, ask Emaar.

Emaar's construction releases give these figures:

  • Barrette piles. More than 145 barrette piles form the foundation, each laid 72 m deep.
  • A record test load. One pile was tested to a load of 36,000 tonnes, which Emaar described as a world record for a single foundation pile.
  • The pile cap. A slab about 20 m thick spreads the tower's load onto the piles. It took about 50,000 cubic metres of concrete, roughly 120,000 tonnes, and about 16,000 tonnes of steel reinforcement.
  • Ahead of schedule. Emaar said concrete placement for the pile cap finished two months ahead of schedule. In January 2018 it reported the cap more than 50% complete, with about 25,000 cubic metres poured and more than 450 people working on site.
Six figures for the Dubai Creek Tower foundations, from Emaar's 2017 and 2018 construction releases: more than 145 barrette piles under the tower's footprint; a pile depth of 72 m for each barrette pile; a single-pile test load of 36,000 tonnes, described by Emaar as a record; a pile cap about 20 m thick that spreads the load onto the piles; 50,000 cubic metres of pile cap concrete, about 120,000 tonnes; and about 16,000 tonnes of steel reinforcement in the pile cap. A note says these are the foundations Emaar reported complete in 2017 and 2018, and the structure above them is a separate stage.
The tower's foundations, in Emaar's figures.

What a barrette pile is. A barrette is a rectangular reinforced concrete pile cast in a deep trench. Tall towers use them to carry heavy loads down to firmer ground.

What a pile cap does. It is a thick concrete slab that sits on top of the piles and spreads the weight of the structure across all of them. Once it is in place, the tower above it can start.

04What is the official timeline for Dubai Creek Tower and Creek Harbour?

The dated milestones run from the design unveiling in April 2016 to the pile cap in 2018, followed by Dubai Square's design in 2024 and the Blue Line metro works from 2025. The metro has a fixed opening date, 9 September 2029. For the tower's completion, ask Emaar.

Timeline of official milestones for Dubai Creek Tower and Dubai Creek Harbour from 2016 to 2029. April 2016: Emaar presents the tower by Santiago Calatrava Valls. July 2016: Emaar reports up to 12 analysis and testing methods by two independent wind tunnel agencies. October 2016: the Ruler of Dubai marks the groundbreaking. March 2017: more than 145 barrette piles complete, one tested to over 36,000 tonnes. January 2018: pile cap more than 50% poured, about 25,000 cubic metres of concrete placed. 2018: pile cap concrete placement finished two months ahead of schedule. February 2024: Emaar completes Dubai Square's detailed design, to be linked to the tower. June 2025: Blue Line foundation stone laid, with the Creek Harbour stop named Emaar Properties Station. 9 September 2029: the RTA's planned start of Blue Line service. A note says a completion date or final height for the tower is not on the timeline and to ask Emaar for its current position.
Dated milestones from Emaar, the RTA and the Dubai Media Office. The 2029 date is the metro's, not the tower's.
The Dubai Creek Tower and Creek Harbour timeline, using only dated official statements.
DateMilestoneStated by
10 April 2016Design by Santiago Calatrava Valls unveiled for Dubai Creek HarbourEmaar
27 July 2016Wind tunnel and structural tests reported complete: up to 12 analysis and testing methods, two independent agenciesEmaar
October 2016Groundbreaking by the Ruler of DubaiEmaar
27 March 2017Pile foundations complete: more than 145 barrette pilesEmaar
23 January 2018Progress reviewed by the Ruler of Dubai; pile cap more than 50% completeEmaar
2018Pile cap complete, two months ahead of scheduleEmaar
7 February 2024Detailed design of Dubai Square complete; to be linked directly to the towerEmaar
9 June 2025Foundation stone of the Dubai Metro Blue Line, including Emaar Properties Station in Creek HarbourDubai Media Office
9 September 2029Planned opening of the Blue LineRTA

About dates you see elsewhere. Articles and adverts often quote a height, a redesign or an opening year for the tower. Unless Emaar or the Dubai Media Office has said it, treat it as unconfirmed. Before you rely on any of it, ask Emaar or your agent for the official document behind the claim.

05How tall will Dubai Creek Tower be?

We do not quote a height. In July 2016 Emaar said its wind tunnel and structural tests would help define the final height; the current design height is on request from Emaar.

The July 2016 release described what the tests covered: a full-scale model of the whole project, separate sections of the building, a wind climate study at several heights, and seismic studies applied to local ground conditions. Emaar said the design used multiple damper and shock absorption systems at different points and heights.

If height matters to your decision, for example because you are paying for a particular view, ask Emaar for the current design in writing.

06What is Dubai Square, and how does it relate to the tower?

Dubai Square is the shopping and entertainment destination Emaar is planning in the centre of Dubai Creek Harbour. In February 2024 Emaar said it had completed Dubai Square's detailed design.

Emaar's release said Dubai Square will be linked directly to Dubai Creek Tower and that the two are being built at the same time. It described Dubai Square as set to become one of the largest shopping and entertainment destinations in the community. Its size and opening date are on request from Emaar.

07Will the tower affect my handover in Dubai Creek Harbour?

No. Each residential building in Dubai Creek Harbour is a separate project with its own registration, escrow account and completion date. Progress on the tower does not change any of them.

Under Law No. 8 of 2007, a developer must register each off-plan project with the Dubai Land Department and pay buyers' money into an escrow account opened for that project. Money is released against certified construction progress on that project, not on the community as a whole.

Your sale and purchase agreement (SPA) gives an anticipated completion date for your building, usually with a grace period. That is the date to plan around. Our guide to the off-plan handover process in Dubai explains what happens when it arrives.

08What does the tower mean if I buy in Dubai Creek Harbour?

Buy on what your contract gives you: the unit, the building, the completion date and the community facilities described in the SPA. A landmark planned nearby is not part of that contract.

That matters most in three places.

Views. If a unit is marketed for a view of the tower or the skyline, the SPA almost never promises that view or what will be built around it. Check the unit's orientation on the floor plan and the community master plan, and ask whether neighbouring plots are planned for taller buildings.

Price. Price the home against similar homes in the community and nearby, not against a landmark that is not yet built. Dubai Land Department registered sales show what comparable homes have sold for.

Marketing claims. Brochures sometimes describe future landmarks, schools, malls or transport as if they were finished. Ask which of them are complete, which are under construction and which are plans, and ask for the source of any date.

The checks below apply to any off-plan purchase in Dubai. Our step-by-step guide to buying off-plan property in Dubai covers the full process, and how to check an off-plan project and developer shows how to verify a project's registration.

09What is in Dubai Creek Harbour today?

Emaar plans Dubai Creek Harbour around a marina, waterfront promenades, parks and branded hotels, with homes in apartment towers and some townhouses. It puts the community at 7.4 million sqm of residential space and 500,000 sqm of parks and open spaces.

Emaar's community page names Dubai Creek Marina, Dubai Creek Park and Creek Beach, and hotels and branded residences including Vida Creek Harbour, Address Harbour Point and Palace Residences. It lists schools, healthcare facilities, shops and restaurants among the community's amenities.

Emaar lists road connections to Al Khail Road and Sheikh Mohammed Bin Zayed Road, which link the community to Downtown Dubai, Dubai Sports City and the inland districts.

10Will Dubai Creek Harbour have a metro station?

Yes. The Dubai Metro Blue Line stops in Dubai Creek Harbour at Emaar Properties Station, which the RTA plans to open with the line on 9 September 2029.

The Dubai Media Office describes the station as 74 metres tall and 11,000 square metres in area, and calls it the world's tallest metro station. It is designed for up to 160,000 passengers a day, with more than 70,000 daily users expected by 2040, and serves about 40,000 Dubai Creek Harbour residents. The naming rights run from its inauguration in 2029.

The station sits on Route 1 of the Blue Line, between Dubai Festival City and Ras Al Khor. The line crosses Dubai Creek on a 1.3 km bridge, the metro's first, and joins the Green Line at Creek station in Al Jaddaf. The RTA says journeys to Dubai International Airport from the areas the line serves take about 20 minutes.

Stations, routes and progress are in our guide to the Dubai Metro Blue Line.

11Which off-plan projects are on sale in Dubai Creek Harbour?

Emaar is the master developer and builds the residential towers, mostly one- to three-bedroom apartments with some larger homes and townhouses. The table below updates from the projects we track and verify.

13 off-plan projects in Dubai Creek Harbour on OffPlan Insider, November 2026. Sold-out projects are left out. Ask us for today's prices and availability.
ProjectDeveloperHomesFromPayment planHandoverStatus
Aeon at Dubai Creek HarbourEmaar PropertiesApartmentAED 3.2MOn requestOn requestSelling
AlberoEmaar PropertiesApartment · TownhouseAED 1.81M10/70/20On requestSelling
AltanEmaar PropertiesApartment · TownhouseAED 1.81M10/70/20On requestSelling
Altus at Dubai Creek HarbourEmaar PropertiesApartmentAED 3.99MOn requestOn requestSelling
Creek Bay at Dubai Creek HarbourEmaar PropertiesApartmentAED 3.25M10/70/20Apr 2030Selling
Creek Haven at Dubai Creek HarbourEmaar PropertiesApartmentAED 2.72M10/70/20Mar 2030Selling
Creek Waters 2 at Dubai Creek HarbourEmaar PropertiesApartment · Townhouse · Penthouse · DuplexAED 3.13MOn requestOn requestSelling
Lyvia by Palace at Dubai Creek HarbourEmaar PropertiesApartment · Townhouse · Branded residenceAED 2.68M10/70/20Jul 2029Selling
Montiva by Vida at Dubai Creek HarbourEmaar PropertiesApartment · Branded residenceAED 1.92M10/70/20Sep 2029Selling
Palace Residences Creek BlueEmaar PropertiesApartment · Branded residenceAED 1.87MOn requestOn requestSelling
Silva at Dubai Creek HarbourEmaar PropertiesApartment · TownhouseAED 1.79MOn requestOn requestSelling
Valia at Dubai Creek HarbourEmaar PropertiesApartmentAED 1.96MOn requestOn requestNew launch
Valo at Dubai Creek HarbourEmaar PropertiesApartment · TownhouseAED 1.89MOn requestOn requestSelling

Each project page has the payment plan, unit types and expected handover. Projects include Creek Bay, Silva, Altan and Valo. For Emaar's whole portfolio, see the Emaar Properties developer page. For other districts, browse all off-plan projects or the latest launches.

12Checklist: buying a Creek Harbour home marketed with the tower

  1. Confirm the project, not the landmark. Find your building on the Dubai Land Department's register and check its escrow account before paying anything.
  2. Read the completion clause. Note the anticipated completion date and the grace period in the SPA. Nothing about the tower should appear in it.
  3. Check the orientation. Use the floor plan and the community master plan to see which way the unit faces and what is planned on neighbouring plots.
  4. Ask for sources in writing. If an adviser quotes a height, a date or a facility, ask for the Emaar or government document behind it.
  5. Compare like with like. Compare price per square foot with similar homes nearby, using Dubai Land Department registered sales.
  6. Plan the handover payment. Know how you will fund the handover instalment, whether in cash or with a mortgage capped at 50% of value on off-plan homes. Our mortgage guide explains the limits.
  7. Budget for ownership. Service charges and utilities start at handover. Our cost guide lists them.
  8. Note the metro date. If transport matters to you, plan on the Blue Line's 9 September 2029 opening, not on earlier assumptions.

13What should I ask Emaar or my agent?

Ask questions whose answers can be checked in a document. A good adviser will answer each one in writing.

Questions to put to the developer or your agent before buying in Dubai Creek Harbour.
QuestionWhy it mattersWhere the answer should come from
What is the anticipated completion date of my building, and the grace period?This is your handover date, not the tower'sThe SPA
Is the project registered, and what is its escrow account?Your instalments must go into the project's escrow accountThe Dubai Land Department register
Which way does the unit face, and what is planned in front of it?Views are rarely promised in the contractThe floor plan and the community master plan
What is the current stage and design of the tower?Height and timing are often quoted without a sourceAn Emaar statement
Which community facilities are open now?Some amenities open in stagesEmaar's community information
How far is the building from Emaar Properties Station?Walking distance decides how useful the metro isThe RTA's station plans and the master plan
What will the service charge be?It starts at handover and is approved by RERAThe developer's estimate, then the Service Charge Index

If you would rather pay part of the price after the keys, our list of post-handover payment plans shows which projects offer them, and our guide to off-plan payment plans compares the structures.

14Key terms

Terms used in this guide.
TermWhat it means here
Master developerThe company that plans and builds the community as a whole. In Dubai Creek Harbour that is Emaar, in a joint venture with Dubai Holding
Master planThe plan for the community's plots, roads, parks and landmarks. Plans can change, and the SPA usually says so
Barrette pileA rectangular reinforced concrete pile cast in a deep trench, used under very tall buildings
Pile capThe thick slab on top of the piles that spreads the load of the structure
Observation deckA public viewing level near the top of a tower. Emaar's design includes the Pinnacle Room and the VIP Observation Garden Decks
SPAThe sale and purchase agreement for your unit, which sets the price, payment plan and completion date
OqoodThe Dubai Land Department's interim register for off-plan sales. It converts to a title deed after handover
Escrow accountThe project bank account your instalments are paid into, released to the developer against certified progress

15How do I follow official news on the tower?

Use primary sources. Emaar publishes its own press releases, and the Dubai Media Office and the RTA publish government announcements, including those on the metro.

For your own building, the Dubai Land Department's Project Status service in the Dubai REST app shows a registered project's certified completion percentage. It is the most reliable way to follow construction of the home you have bought.

If you are weighing Creek Harbour against other districts, our overview of Dubai's areas and districts compares them, and off-plan vs ready property helps if you would rather buy a finished home.

16Where to go next

Start with the Dubai Creek Harbour area page for every project and price in the community, then read the Blue Line guide for the station and route. If you are close to choosing a unit, ask us for today's availability and the official documents for anything you have been told about the tower.

ProjectsProjects mentioned in this guide.

FAQQuestions buyers ask.

Where is Dubai Creek Tower?

Dubai Creek Tower is in Dubai Creek Harbour, Emaar's 6 sq km community on the bank of Dubai Creek, next to the Ras Al Khor Wildlife Sanctuary. Emaar places the community about 10 minutes by car from Dubai International Airport and about 10 to 15 minutes from Downtown Dubai and the Burj Khalifa, depending on traffic.

Is Dubai Creek Tower finished?

No. The milestones Emaar has reported are the pile foundations, completed in March 2017, and the pile cap above them, completed in 2018. For the current stage of works on the tower, ask Emaar directly. Homes in Dubai Creek Harbour are sold in separate residential buildings, each with its own construction schedule.

When will Dubai Creek Tower be completed?

There is no completion date we can give you from an official source, and we do not guess one. Ask Emaar for its current position. If you are buying in Creek Harbour, the date that matters is the completion date of your own building, which is written into your sale and purchase agreement.

How tall will Dubai Creek Tower be?

Emaar said in 2016 that wind tunnel tests would help define the tower's final height. We do not quote a height without an official figure behind it, so ask Emaar for the current design height. Treat any precise figure you see in advertising as unconfirmed until Emaar states it.

Who designed Dubai Creek Tower?

Santiago Calatrava Valls, the Spanish-Swiss architect and engineer. Emaar said in April 2016 that his design was chosen through an international competition. The concept was inspired by the lily, with an oval top on a slender stem anchored to the ground by cables, and observation decks offering 360-degree views.

Is Dubai Creek Harbour freehold?

Yes. Emaar sells homes in Dubai Creek Harbour to buyers of any nationality, and each purchase is registered with the Dubai Land Department, first on the interim Oqood register and then as a title deed after handover. Check that your project and its escrow account appear on the department's register before you pay.

Can I buy an apartment in Dubai Creek Tower?

Emaar's description of the tower centres on observation decks and a boutique hotel rather than homes. The apartments sold in Dubai Creek Harbour are in the residential buildings around it, sold by Emaar under names such as Creek Bay, Silva, Altan and Valo. For anything sold as part of the tower itself, ask Emaar for the official documents.

Will Dubai Creek Harbour have a metro station?

Yes. The Dubai Metro Blue Line has a station in Dubai Creek Harbour, named Emaar Properties Station. The RTA describes it as 74 metres tall and the world's tallest metro station, serving about 40,000 Creek Harbour residents. The line is planned to open on 9 September 2029.

How far is Dubai Creek Tower from the airport?

Emaar puts Dubai Creek Harbour about 10 minutes by car from Dubai International Airport. Once the Blue Line opens, the RTA says journeys to the airport from the areas it serves take about 20 minutes. Driving times vary with traffic and time of day.

Sources & methodWhere these figures come from.

Sources

  1. ma.emaar.com: Emaar designs a glittering new skyline for dubai with compelling tower at dubai creek harbour
  2. sa.emaar.com: Advanced wind tunnel tests confirm structural strength of the tower at dubai creek harbour the new icon by emaar
  3. sa.emaar.com: The new beacon rises emaar completes foundation of the tower at dubai creek harbour
  4. ma.emaar.com: Hh sheikh mohammed bin rashid reviews progress of dubai creek tower
  5. emaar.com: Dubai creek tower sets new milestone with completion of pile cap
  6. emaar.com: Emaar unveils dubai square a futuristic fusion of cutting edge retail entertainment and technology in dubai creek harbour
  7. emaar.com: Dubai creek harbour
  8. communities.emaar.com: About dubai creek harbour
  9. mediaoffice.ae: Mohammed bin rashid lays foundation stone for dubai metro blue line
  10. mediaoffice.ae: Mohammed bin rashid inaugurates tunneling works for the dubai metro blue line tunnels
  11. rta.ae: Announcing the awarding of dubai metro blue line project
  12. Dubai Legislation Portal: Law No. (8) of 2007
  13. Dubai Land Department: Request to register the initial sale

What we could not verify

  • The current construction stage of Dubai Creek Tower, its final height and any completion date could not be confirmed from an Emaar or Dubai Media Office statement on 4 November 2026. Press reports from 2026 about a redesign and a construction tender are not official statements and are not used in the text.
  • The pile cap completion is dated 2018 from the content of Emaar's release, which carries no publication date on the page we opened; the January 2018 release said the pile cap was more than 50% complete.
  • Whether Dubai Creek Harbour is named as a freehold area in Dubai's designated-areas regulation was not checked line by line; the text relies on Emaar selling there to buyers of all nationalities with Dubai Land Department registration.

4 Nov 2026 · Reviewed by OffPlan Insider Research. First published 4 Nov 2026.

Want options that fit your budget?

Tell us your budget and what the property is for. We check live prices, plans and availability with the developers and send the options that fit.

  1. Share your budgetAnd what the property is for
  2. We check with developersPrices, plans and availability
  3. You reserve directBooking and SPA are with the developer

No consultation fee · You book directly with the developer