The Dubai Metro Blue Line is nearly 30 per cent complete and remains on track to open on 9 September 2029. The progress update came on Sunday 22 November, when the Crown Prince of Dubai inspected the works at the Dubai Festival City site. The design of the new Blue Line trains was revealed at the same visit.
A team of 14,000 workers, engineers and supervisors has logged 33 million working hours on the AED 20.5 billion project so far. The opening date marks 20 years since the first Dubai Metro line opened.
01The line at a glance
| Detail | Dubai Metro Blue Line |
|---|---|
| Builder | Roads and Transport Authority (RTA), with the MAPA, Limak and CRRC consortium |
| Cost | AED 20.5 billion |
| Progress | Nearly 30 per cent, November 2026 |
| Length | 30 km, of which 15.5 km underground |
| New stations | 14, taking the network to 78 |
| Network on completion | 131 km, 168 trains |
| Opening | 9 September 2029 |
02The new trains
The Blue Line trains will carry up to 1,246 passengers per journey. Each has a Gold Class, a Silver Class and a carriage for women and children.
Gold Class gets wireless device chargers, digital screens and smart lighting that adjusts to the surroundings. On-board cameras will detect obstacles on the track and count passengers to monitor how full each carriage is.
The stations follow five architectural concepts. The best known is the Emaar Properties Station at Dubai Creek Harbour, which at 74 metres is described as the world's highest metro station.
03Where it runs
The Blue Line connects with the Red and Green lines and crosses Dubai Creek on a new bridge. It serves Mirdif, Dubai Festival City, Dubai Creek Harbour and International City, then runs to Dubai Silicon Oasis and Academic City.
Several of these are among Dubai's busiest off-plan districts. Dubai Creek Harbour has a long pipeline of Emaar towers, and Dubai Silicon Oasis and the land around Academic City are drawing new villa, townhouse and apartment launches.
04What it means for buyers
For homes in these areas due to hand over around 2029, the metro has a set opening date of its own. The works are now close to a third complete, and the RTA has kept the September 2029 date.
Our team can show you the off-plan projects within reach of the planned Blue Line stations, with prices, payment plans and handover dates.
SourcesWhere this story comes from.
Sources
- Khaleej Times: Dubai Metro Blue Line nearly 30% complete; Sheikh Hamdan inspects progress, 22 November 2026
- The National: 'New generation' Dubai Metro Blue Line train unveiled with Dh20.5bn project nearly 30 per cent complete, 22 November 2026
- Gulf News: Gold Class to smart tech: What to expect on Blue Line, 22 November 2026
- Khaleej Times: New design for Dubai Metro Blue Line revealed with upgraded tech, colours, 22 November 2026
Corrections
- No corrections to this story. If something has changed or is wrong, tell us and we will correct it and log the change here.
22 Nov 2026, 20:10 GST · Reported by OffPlan Insider Newsdesk, checked against the developer's own material before publication.