Sobha Realty construction update: Sobha One at 87%, Riverside Crescent towers at 41% to 61%

Sobha Realty's September 2026 update covers 22 Dubai phases, from Creek Vista Heights at 88% overall to the first Sobha Central towers, where piling is complete.

Published 3 min read
The five interconnected Sobha One towers, rising from 30 to 65 storeys
Sobha One in Ras Al Khor, 87% complete overall in September 2026. Render: Sobha Realty.

Sobha Realty has released its construction update for September 2026, covering its Dubai projects phase by phase. Each project is scored on structure, façade, internal finishes and an overall figure.

The most advanced homes are close to the finish. Creek Vista Heights in Sobha Hartland is at 88.1% overall, Verde by Sobha at 86.33% and Sobha One at 87%.

01Overall progress by project

Project Structure Façade Internal finishes Overall
Creek Vista Heights, Sobha Hartland 100% 100% 79% 88.1%
Verde by Sobha 100% 97% 78% 86.33%
Sobha One 99.8% 53.2% 71.2% 87%
The Sobha Element, Sobha One 17.92% Not started 1.62% 6.38%
Sobha Reserve (villas) 100% 45% 65.6% 81.2%
Sobha Hartland II villas, Phase 1.1 100% 90.7% 92% 94.43%
Sobha Hartland II villas, Phase 1.2 100% 25.35% 38.63% 53.4%
Sobha Hartland II villas, Phase 2 100% Not started 4.95% 25.94%
330 Riverside Crescent 99.4% 49% 49% 61%
320 Riverside Crescent 93% 39% 41% 52%
340 Riverside Crescent 98% 48% 31% 52%
350 Riverside Crescent 92% 48% 33% 50%
360 Riverside Crescent 90% 37.5% 26% 43%
310 Riverside Crescent 84% 34% 27% 41%
Sobha SeaHaven 77% 14% 16.1% 29.74%
Skyscape Altius, Aura and Avenue 66% 4.6% 13% 27%
Sobha Orbis 55.01% 4.82% 16.41% 21%
Sobha Elwood (villas) 39.61% 1% 6.52% 18%
Sobha Solis 25.57% Not started 1.04% 10.19%
Skyvue 24% Not started 0.5% 7%
Sobha Central: The Eden and The Horizon 19% Not started Not started 7.5%
Sobha Central: The Tranquil and The Serene 17% Not started Not started 6.74%

02Highlights

At Sobha Reserve, structure is complete on all 340 villas and the Building Completion Certificate has been received for 101 of them. Testing, commissioning and snagging are under way on 124 villas.

At Sobha One, the five towers and the link towers are structurally complete. Work continues on the Skygarden and roof levels.

The six Riverside Crescent towers in Sobha Hartland II are all past 84% structure, with façade and internal finishes running on every tower.

03Earlier stages

Construction is moving on the newer launches too. At Sobha Elwood, first-floor works are under way on 122 villas and roof works on 121. Sobha Solis has reached Level 7 to Level 11 across its four towers, and Skyvue's most advanced tower is at Level 14.

At Sobha Central on Sheikh Zayed Road, shoring and piling are complete for all four towers, and excavation is in progress at The Eden and The Horizon.

04What it means for buyers

On a construction-linked payment plan, instalments fall due as these milestones are reached. Overall progress is a fair guide to how soon the next ones will come. Check the stage of your own tower or villa series with the developer, since figures differ within a project.

See all Sobha Realty projects and payment plans across the UAE.

ProjectsProjects in this story.

SourcesWhere this story comes from.

Sources

  1. Sobha Realty: Construction Update, Dubai Projects, September 2026 (shared with OffPlan Insider), 29 October 2026

Corrections

  • No corrections to this story. If something has changed or is wrong, tell us and we will correct it and log the change here.

29 Oct 2026, 19:02 GST · Reported by OffPlan Insider Newsdesk, checked against the developer's own material before publication.

Want the details on Sobha One?

We confirm current prices, plans and availability directly with the developer, then send you what fits.

  1. We check with the developerToday’s units, prices and plan
  2. You get the detailsBy phone or email, your choice
  3. You reserve directBooking is with the developer

No consultation fee · You book directly with the developer